Edmondson Ranch Wind
BetaSuspendedWindERCOTLBNL
293.28 MW generation in Glasscock, TX · In queue since October 2016
293.28 MW
Capacity
1
Components
Wind
9y 5m
In Queue
IA Executed
IA Status
Signed Sep 2017
Interconnection Timeline
Queue → IA
11 months
Total Duration
11 months
Suspended75%
Queue EntryOct 26, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementSep 28, 2017
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–36 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
TX
County
Glasscock
Region
ERCOT
Developer
Lacy Creek Wind, LLC
Utility
—
Entity
ERCOT
Data Source
LBNL