Maryneal Wind
182.4 MW generation in Nolan, TX · In queue since May 2016 · Proposed COD July 2025
182.4 MW
Capacity
1
Components
Wind
9y 11m
In Queue
IA Executed
IA Status
Signed Jan 2020
Queue → IA
3y 8m
IA → COD
5y 6m
Total Duration
3y 8m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2025-07-31
State
TX
County
Nolan
Region
ERCOT
Developer
Maryneal Windpower, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
71050 Bitter Creek 345kV
Data Source
LBNL + Live
Linked EIA Plant
Maryneal Windpower
EIA Plant ID: 62836
Last updated 2026-03-26