Armstrong Wind
253 MW generation in Armstrong, TX · In queue since May 2016
253 MW
Capacity
1
Components
Wind
9y 10m
In Queue
IA Executed
IA Status
Signed Aug 2018
Queue → IA
2y 3m
Total Duration
2y 3m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–36 months
Commercial operation date not yet determined
State
TX
County
Armstrong
Region
ERCOT
Developer
Big Sky Energy
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 79500 Alibates - 79503 Tule Canyon
Data Source
LBNL
Armstrong County AI data center project scaled back from original plan
CLAUDE, Texas (KFDA) - Armstrong County commissioners approved an amendment Tuesday to Crusoe Energy's tax abatement agreement for an AI...
Brazilian company SERENA propels Texas' wind energy growth with billion-dollar investment in Armstrong County
A massive investment overseen by SERENA a company based out of Brazil and in Austin, Texas has the potential to grow bigger citing economic climate in the...
Brazilian company SERENA propels Texas' wind energy growth with billion-dollar investment in Armstrong County
A massive investment overseen by SERENA a company based out of Brazil and in Austin, Texas has the potential to grow bigger citing economic climate in the...
Hannon Armstrong Invests in 1.6 GW Renewable Energy Portfolio Developed and Managed by Clearway Energy Group
A leading investor in climate solutions, today announced a preferred equity investment in an approximately 1.6 gigawatt (GW) onshore wind and utility-scale...
Last updated 2026-03-26