Desert Sky repower
ERCOT-17INR0070BetaActiveWindERCOTLBNL + Live
7.2 MW generation in Pecos, TX · In queue since November 2017 · Proposed COD May 2023
7.2 MW
Capacity
1
Components
Wind
8y 5m
In Queue
IA Executed
IA Status
Signed Oct 2018
Interconnection Timeline
Queue → IA
11 months
IA → COD
4y 7m
Total Duration
11 months
Schedule
35 months past proposed COD
Construction75%
Queue EntryNov 8, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 18, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2023-05-16
Project Details
State
TX
County
Pecos
Region
ERCOT
Developer
DESERT SKY WIND FARM LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
two LCRA 138kV
Data Source
LBNL + Live