Trent repower
ERCOT-17INR0069BetaActiveWindERCOTLBNL + Live
6.4 MW generation in Nolan, TX · In queue since November 2017 · Proposed COD January 2026
6.4 MW
Capacity
1
Components
Wind
8y 5m
In Queue
IA Executed
IA Status
Signed Oct 2018
Interconnection Timeline
Queue → IA
11 months
IA → COD
7y 3m
Total Duration
11 months
Schedule
3 months past proposed COD
Construction75%
Queue EntryNov 8, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 19, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-01-01
Project Details
State
TX
County
Nolan
Region
ERCOT
Developer
TRENT WIND FARM LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
1338 Eskota 138kV
Data Source
LBNL + Live
No news available for this project.