Capricorn IV repower
BetaActiveWindERCOTLBNL
9 MW generation in Sterling, TX · In queue since August 2017 · Proposed COD May 2022
9 MW
Capacity
1
Components
Wind
8y 7m
In Queue
IA Executed
IA Status
Signed Jan 2008
Interconnection Timeline
IA → COD
14y 4m
Total Duration
8y 7m
Schedule
47 months past proposed COD
Construction75%
Queue EntryAug 23, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJan 15, 2008
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2022-05-31
Project Details
State
TX
County
Sterling
Region
ERCOT
Developer
Nextera
Utility
—
Entity
ERCOT
Point of Interconnection
76090 Divide 345kV
Data Source
LBNL
No news available for this project.