Capricorn I & III repower
ERCOT-17INR0054BetaActiveWindERCOTLBNL + Live
32 MW generation in Sterling, TX · In queue since March 2017 · Proposed COD May 2026
32 MW
Capacity
1
Components
Wind
9y 1m
In Queue
IA Executed
IA Status
Signed Nov 2006
Interconnection Timeline
IA → COD
19y 6m
Total Duration
9y 1m
Construction75%
Queue EntryMar 9, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 14, 2006
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-05-31
Project Details
State
TX
County
Sterling
Region
ERCOT
Developer
Nextera
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
180757 Capricorn Ridge 3 138kV
Data Source
LBNL + Live
No news available for this project.