Horse13 CallD repower
ERCOT-17INR0052BetaActiveWindERCOTLBNL + Live
44 MW generation in Taylor, TX · In queue since October 2016 · Proposed COD September 2026
44 MW
Capacity
1
Components
Wind
9y 6m
In Queue
IA Executed
IA Status
Signed May 2019
Interconnection Timeline
Queue → IA
2y 7m
IA → COD
7y 4m
Total Duration
2y 7m
Construction75%
Queue EntryOct 3, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementMay 22, 2019
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-09-30
Project Details
State
TX
County
Taylor
Region
ERCOT
Developer
Nextera
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
6216 Bluff Creek 138kV
Data Source
LBNL + Live