Vaquero 1 Wind
BetaActiveWindERCOTLBNL + Live
400 MW generation in Zapata, TX · In queue since April 2016 · Proposed COD January 2027
400 MW
Capacity
1
Components
Wind
9y 11m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
10y 9m
Facilities Study50%
Queue EntryApr 1, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-01-15
Project Details
State
TX
County
Zapata
Region
ERCOT
Developer
Enerverse
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 8905 N Edinb - 8455 Lon Hill
Data Source
LBNL + Live
No news available for this project.