Wake Solar — Project Summary

Queue ID
ERCOT-16INR0119
Capacity
150 MW
Technology
Solar
Status
suspended
Location
Crosby, TX
Region
ERCOT
Developer
Invenergy
IA Status
Facility Study

Wake Solar

BetaSuspendedSolarERCOTLBNL

150 MW generation in Crosby, TX · In queue since July 2015

150 MW

Capacity

1

Components

Solar

10y 8m

In Queue

Facility Study

IA Status

Interconnection Timeline

Total Duration

10y 8m

Suspended50%
Queue EntryJul 20, 2015

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

TX

County

Crosby

Region

ERCOT

Developer

Invenergy

Utility

Entity

ERCOT

Point of Interconnection

59904 Cottonwood 345kV

Data Source

LBNL