Wake Solar
150 MW generation in Crosby, TX · In queue since July 2015
150 MW
Capacity
1
Components
Solar
10y 8m
In Queue
Facility Study
IA Status
Total Duration
10y 8m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
State
TX
County
Crosby
Region
ERCOT
Developer
Invenergy
Utility
—
Entity
ERCOT
Point of Interconnection
59904 Cottonwood 345kV
Data Source
LBNL
ArcLight Capital Partners: Acquisition Of 5.4 Billion Power Portfolio Stake From InfraBridge
ArcLight Capital Partners has agreed to acquire InfraBridge's 50% stake in Invenergy AMPCI Thermal Power (IATP), a large-scale portfolio of...
ArcLight to buy InfraBridge’s stake in North American power assets
ArcLight Capital Partners has signed an agreement to acquire InfraBridge's 50% stake in Invenergy AMPCI Thermal Power (IATP).
NVIDIA backs AI factories designed to come online faster and support the grid
NVIDIA (NVDA) and Emerald AI announced a collaboration with AES, Constellation, Invenergy, NextEra Energy, Nscale Energy & Power and Vistra...
Major US Solar and Storage Projects Advance in 2026: Google, Sunraycer, Invenergy Lead Development
A roundup of major US renewable energy projects announced or advancing in early 2026, featuring solar-plus-storage developments from Google,...
Last updated 2026-03-14