Loma Pinta Wind
ERCOT-16INR0112BetaActiveWindERCOTLBNL + Live
197.01 MW generation in La Salle, TX · In queue since May 2015 · Proposed COD December 2026
197.01 MW
Capacity
1
Components
Wind
10y 11m
In Queue
IA Executed
IA Status
Signed Dec 2017
Interconnection Timeline
Queue → IA
2y 7m
IA → COD
9 years
Total Duration
2y 7m
Construction75%
Queue EntryMay 18, 2015
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 13, 2017
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
La Salle
Region
ERCOT
Developer
Enerverse
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
5705 Fowlerton 138kV
Data Source
LBNL + Live
No news available for this project.