Whatley Solar
BetaSuspendedSolarERCOTLBNL
150 MW generation in Andrews, TX · In queue since May 2015
150 MW
Capacity
1
Components
Solar
10y 10m
In Queue
Facility Study
IA Status
Interconnection Timeline
Total Duration
10y 10m
Suspended50%
Queue EntryMay 5, 2015
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
TX
County
Andrews
Region
ERCOT
Developer
Invenergy
Utility
—
Entity
ERCOT
Point of Interconnection
1281 Amoco Midland tap 69kV
Data Source
LBNL
No news available for this project.