Mesteno Wind
201.6 MW generation in Starr, TX · In queue since December 2014 · Proposed COD June 2025
201.6 MW
Capacity
1
Components
Wind
11y 4m
In Queue
IA Executed
IA Status
Signed Apr 2018
Queue → IA
3y 4m
IA → COD
7y 2m
Total Duration
3y 4m
Schedule
9 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 18–36 months
Proposed COD: 2025-06-30
State
TX
County
Starr
Region
ERCOT
Developer
Mesteno Windpower, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
80355 Del Sol 345kV
Data Source
LBNL + Live
Linked EIA Plant
Mesteno
EIA Plant ID: 62258
Last updated 2026-03-14