Nazareth Solar
ERCOT-16INR0049BetaActiveSolarERCOTLBNL + Live
204 MW generation in Castro, TX · In queue since June 2014 · Proposed COD August 2027
204 MW
Capacity
1
Components
Solar
11y 10m
In Queue
IA Executed
IA Status
Signed Jun 2023
Interconnection Timeline
Queue → IA
9 years
IA → COD
4y 2m
Total Duration
9 years
Construction75%
Queue EntryJun 19, 2014
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJun 7, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-08-05
Project Details
State
TX
County
Castro
Region
ERCOT
Developer
TX Nazareth Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 23914 Tule Canyon - 23912 Ogallala C2
Data Source
LBNL + Live