Harald (BearKat Wind B)
ERCOT-15INR0064bBetaActiveWindERCOTLBNL + Live
162.1 MW generation in Glasscock, TX · In queue since November 2013 · Proposed COD April 2026
162.1 MW
Capacity
1
Components
Wind
12y 5m
In Queue
IA Executed
IA Status
Signed May 2018
Interconnection Timeline
Queue → IA
4y 6m
IA → COD
7y 11m
Total Duration
4y 6m
Construction75%
Queue EntryNov 27, 2013
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementMay 30, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-04-30
Project Details
State
TX
County
Glasscock
Region
ERCOT
Developer
CIP
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
59903 Bearkat 345kV
Data Source
LBNL + Live