Tierra Blanca W
BetaSuspendedWindERCOTLBNL
200 MW generation in Randall, TX · In queue since October 2013
200 MW
Capacity
1
Components
Wind
12y 5m
In Queue
Facility Study
IA Status
Interconnection Timeline
Total Duration
12y 5m
Suspended50%
Queue EntryOct 1, 2013
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
TX
County
Randall
Region
ERCOT
Developer
RWE Renewables Development, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
79501 Ogallala 345kV
Data Source
LBNL
No news available for this project.