Goodnight Wind
531 MW generation in Armstrong, TX · In queue since July 2012
531 MW
Capacity
1
Components
Wind
13y 8m
In Queue
IA Executed
IA Status
Signed Aug 2019
Queue → IA
7y 1m
Total Duration
7y 1m
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction pending
Typical: 18–36 months
Commercial operation date not yet determined
State
TX
County
Armstrong
Region
ERCOT
Developer
FGE Goodnight I, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 79500 Alibates - 79503 Tule Canyon CKT2
Data Source
LBNL
Serena starts commissioning 265.5-MW wind farm in Texas
Brazilian energy firm Serena (BVMF:SRNA3) has announced that all turbines at the 265.5-MW Goodnight 1 wind power plant in Texas have been...
More Windmills for the Texas Panhandle
The Goodnight Wind Energy project will be bringing more wind turbines in the the Texas Panhandle and more jobs.
More Windmills for the Texas Panhandle
The Goodnight Wind Energy project will be bringing more wind turbines in the the Texas Panhandle and more jobs.
FGE Power Announces Sale of FGE Goodnight Wind Farm Project to Omega Energia
FGE Power, LLC (Austin-based developers of large-scale renewable energy projects) announces the sale of 100% ownership of FGE Goodnight wind project to Omega...