HOVEY (Barilla Solar 1B)
BetaActiveSolarERCOTLBNL
7.4 MW generation in Pecos, TX · In queue since December 2010 · Proposed COD March 2025
7.4 MW
Capacity
1
Components
Solar
15y 3m
In Queue
IA Executed
IA Status
Signed Dec 2013
Interconnection Timeline
Queue → IA
3 years
IA → COD
11y 3m
Total Duration
3 years
Schedule
12 months past proposed COD
Construction75%
Queue EntryDec 1, 2010
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 26, 2013
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-03-31
Project Details
State
TX
County
Pecos
Region
ERCOT
Developer
First Solar
Utility
—
Entity
ERCOT
Point of Interconnection
60385 Solstice 138kV
Data Source
LBNL
No news available for this project.