AN50B — Project Summary

Queue ID
EPE-LG-24-3-9
Capacity
50 MW
Technology
Battery
Status
active
Location
Luna, NM
Region
West
Developer
IA Status
In Progress (unknown study)

AN50B

BetaActiveBatteryEPELBNL

50 MW storage in Luna, NM · In queue since March 2024 · Proposed COD December 2027

50 MW

Capacity

1

Components

Battery

2 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 9m

In Study38%
Queue EntryMar 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

NM

County

Luna

Region

West

Developer

Utility

El Paso Electric Company

Entity

EPE

Point of Interconnection

Afton-Newman 345kV Line

Data Source

LBNL