Co200B — Project Summary

Queue ID
EPE-LG-24-3-5
Capacity
200 MW
Technology
Battery
Status
active
Location
El Paso, TX
Region
West
Developer
IA Status
In Progress (unknown study)

Co200B

BetaActiveBatteryEPELBNL

200 MW storage in El Paso, TX · In queue since March 2024 · Proposed COD April 2026

200 MW

Capacity

1

Components

Battery

2 years

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2y 1m

In Study38%
Queue EntryMar 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-04-01

Project Details

State

TX

County

El Paso

Region

West

Developer

Utility

El Paso Electric Company

Entity

EPE

Point of Interconnection

Marvin 115 KV Substation

Data Source

LBNL

No news available for this project.