AN100S
BetaActiveSolarEPELBNL
100 MW generation in Luna, NM · In queue since March 2024 · Proposed COD December 2027
100 MW
Capacity
1
Components
Solar
2 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 9m
In Study38%
Queue EntryMar 27, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
NM
County
Luna
Region
West
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Point of Interconnection
Afton-Newman 345kV Line
Data Source
LBNL
No news available for this project.