Sf250SB — Project Summary

Queue ID
EPE-LG-23-9-4
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Hudspeth, TX
Region
West
Developer
IA Status
Facility Study

Sf250SB

BetaActiveSolarBatteryEPELBNL

250 MW hybrid in Hudspeth, TX · In queue since September 2023 · Proposed COD December 2028

250 MW

Capacity

1

Components

Solar

2y 6m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 3m

Facilities Study50%
Queue EntrySep 29, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

TX

County

Hudspeth

Region

West

Developer

Utility

El Paso Electric Company

Entity

EPE

Point of Interconnection

San Felipe 115kV Substation

Data Source

LBNL

No news available for this project.