AW300S — Project Summary

Queue ID
EPE-LG-23-3-2
Capacity
300 MW
Technology
Solar
Status
active
Location
Sierra, NM
Region
West
Developer
IA Status
IA Executed

AW300S

BetaActiveSolarEPELBNL

300 MW generation in Sierra, NM · In queue since March 2023 · Proposed COD December 2026

300 MW

Capacity

1

Components

Solar

3 years

In Queue

IA Executed

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 9m

Construction75%
Queue EntryMar 31, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

NM

County

Sierra

Region

West

Developer

Utility

El Paso Electric Company

Entity

EPE

Point of Interconnection

Westmesa-Arroyo 345kV

Data Source

LBNL