LH252W
BetaActiveWindEPELBNL
252 MW generation in Grant, NM · In queue since March 2023 · Proposed COD March 2027
252 MW
Capacity
1
Components
Wind
3 years
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4 years
Construction75%
Queue EntryMar 14, 2023
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2027-03-31
Project Details
State
NM
County
Grant
Region
West
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Point of Interconnection
Hidalgo-Luna 345 kV line
Data Source
LBNL
No news available for this project.