VS75SB
BetaActiveSolarBatteryEPELBNL
75 MW hybrid in Dona Ana, NM · In queue since September 2022 · Proposed COD December 2026
75 MW
Capacity
1
Components
Solar
3y 6m
In Queue
IA Pending
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 3m
In Study38%
Queue EntrySep 30, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
NM
County
Dona Ana
Region
West
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Point of Interconnection
Salopek-Vado 115kV line
Data Source
LBNL
No news available for this project.