SS100S
BetaActiveSolarEPELBNL
100 MW generation in El Paso, TX · In queue since September 2022 · Proposed COD August 2025
100 MW
Capacity
1
Components
Solar
3y 6m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 11m
Schedule
7 months past proposed COD
Construction75%
Queue EntrySep 30, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-08-29
Project Details
State
TX
County
El Paso
Region
West
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Point of Interconnection
Seabeck-San Felipe 115kV line
Data Source
LBNL
No news available for this project.