LA300W — Project Summary

Queue ID
EPE-LG 22-3-6
Capacity
300 MW
Technology
Wind
Status
suspended
Location
Luna, NM
Region
West
Developer
IA Status
Suspended

LA300W

BetaSuspendedWindEPELBNL

300 MW generation in Luna, NM · In queue since March 2022 · Proposed COD December 2028

300 MW

Capacity

1

Components

Wind

4 years

In Queue

Suspended

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6y 9m

Suspended38%
Queue EntryMar 31, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-15

Project Details

State

NM

County

Luna

Region

West

Developer

Utility

El Paso Electric Company

Entity

EPE

Point of Interconnection

Luna-Afton 345kV

Data Source

LBNL

No news available for this project.