VE50S Project
BetaActiveSolarEPELBNL
50 MW generation in Dona Ana, NM · In queue since September 2019 · Proposed COD December 2025
50 MW
Capacity
1
Components
Solar
6y 6m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
6y 3m
Schedule
4 months past proposed COD
Construction75%
Queue EntrySep 25, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-12-05
Project Details
State
NM
County
Dona Ana
Region
West
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Point of Interconnection
Verde 115kV Substation
Data Source
LBNL
No news available for this project.