LA130S Project
BetaActiveSolarEPELBNL
130 MW generation in Luna, NM · In queue since March 2019 · Proposed COD August 2025
130 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Pending
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
6y 5m
Schedule
7 months past proposed COD
In Study38%
Queue EntryMar 25, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-08-31
Project Details
State
NM
County
Luna
Region
West
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Point of Interconnection
Luna-Afton 345kV
Data Source
LBNL
No news available for this project.