AC120SB Project — Project Summary

Queue ID
EPE-LG-17-9-3
Capacity
120 MW
Technology
Solar+Battery
Status
active
Location
Otero, NM
Region
West
Developer
IA Status
IA Executed

AC120SB Project

BetaActiveSolarBatteryEPELBNL

120 MW hybrid in Otero, NM · In queue since September 2017 · Proposed COD June 2022

120 MW

Capacity

1

Components

Solar

8y 6m

In Queue

IA Executed

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

4y 9m

Schedule

46 months past proposed COD

Construction75%
Queue EntrySep 27, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2022-06-05

Project Details

State

NM

County

Otero

Region

West

Developer

Utility

El Paso Electric Company

Entity

EPE

Point of Interconnection

Otero 345kV Substation

Data Source

LBNL

No news available for this project.