AC120SB Project
BetaActiveSolarBatteryEPELBNL
120 MW hybrid in Otero, NM · In queue since September 2017 · Proposed COD June 2022
120 MW
Capacity
1
Components
Solar
8y 6m
In Queue
IA Executed
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
4y 9m
Schedule
46 months past proposed COD
Construction75%
Queue EntrySep 27, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2022-06-05
Project Details
State
NM
County
Otero
Region
West
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Point of Interconnection
Otero 345kV Substation
Data Source
LBNL