D150S Project — Project Summary

Queue ID
EPE-LG-17-9-1
Capacity
150 MW
Technology
Solar+Battery
Status
active
Location
Dona Ana, NM
Region
West
Developer
IA Status
IA Executed

D150S Project

BetaActiveSolarBatteryEPELBNL

150 MW hybrid in Dona Ana, NM · In queue since September 2017 · Proposed COD September 2025

150 MW

Capacity

1

Components

Solar

8y 6m

In Queue

IA Executed

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

8 years

Schedule

6 months past proposed COD

Construction75%
Queue EntrySep 6, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Proposed COD: 2025-09-15

Project Details

State

NM

County

Dona Ana

Region

West

Developer

Utility

El Paso Electric Company

Entity

EPE

Point of Interconnection

Diablo 115 kV Substation

Data Source

LBNL

No news available for this project.