D150S Project
BetaActiveSolarBatteryEPELBNL
150 MW hybrid in Dona Ana, NM · In queue since September 2017 · Proposed COD September 2025
150 MW
Capacity
1
Components
Solar
8y 6m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
8 years
Schedule
6 months past proposed COD
Construction75%
Queue EntrySep 6, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–30 months
Commercial Operation
Proposed COD: 2025-09-15
Project Details
State
NM
County
Dona Ana
Region
West
Developer
—
Utility
El Paso Electric Company
Entity
EPE
Point of Interconnection
Diablo 115 kV Substation
Data Source
LBNL