BetaActiveSolarDukeLBNL
74.9 MW generation in Chesterfield, SC · In queue since September 2024 · Proposed COD October 2026
74.9 MW
Capacity
1
Components
Solar
1y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
2y 1m
In Study38%
Queue EntrySep 4, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-10-15
Project Details
State
SC
County
Chesterfield
Region
Southeast
Developer
—
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
Robinson Plant - Rockingham
Data Source
LBNL
No news available for this project.