14 MW generation in Liberty, FL · In queue since February 2009 · Proposed COD June 2009
14 MW
Capacity
1
Components
Other
17y 1m
In Queue
IA Executed
IA Status
COD target: 2009
Interconnection Timeline
Total Duration
4 months
Schedule
205 months past proposed COD
Construction75%
Queue EntryFeb 10, 2009
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–36 months
Commercial Operation
Proposed COD: 2009-06-01
Project Details
State
FL
County
Liberty
Region
Southeast
Developer
Telogia Biomass
Utility
Duke Energy Florida
Entity
Duke
Point of Interconnection
Liberty Substation
Data Source
LBNL