— Project Summary

Queue ID
Duke-963473
Capacity
44 MW
Technology
Solar
Status
active
Location
Greenville, SC
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarDukeLBNL

44 MW generation in Greenville, SC · In queue since September 2024

44 MW

Capacity

1

Components

Solar

1y 6m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 6m

Impact Study25%
Queue EntrySep 30, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

SC

County

Greenville

Region

Southeast

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Point of Interconnection

RABON BL 100kV

Data Source

LBNL

No news available for this project.