— Project Summary

Queue ID
Duke-963122
Capacity
50 MW
Technology
Solar
Status
active
Location
Laurens, SC
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarDukeLBNL

50 MW generation in Laurens, SC · In queue since September 2024

50 MW

Capacity

1

Components

Solar

1y 6m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 6m

Impact Study25%
Queue EntrySep 26, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

SC

County

Laurens

Region

Southeast

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Point of Interconnection

CLINTON 100kV

Data Source

LBNL

No news available for this project.