— Project Summary

Queue ID
Duke-962978
Capacity
20 MW
Technology
Solar
Status
active
Location
Greenwood, SC
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarDukeLBNL

20 MW generation in Greenwood, SC · In queue since September 2024

20 MW

Capacity

1

Components

Solar

1y 6m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 6m

Impact Study25%
Queue EntrySep 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

SC

County

Greenwood

Region

Southeast

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Data Source

LBNL

No news available for this project.