— Project Summary

Queue ID
Duke-962966
Capacity
55 MW
Technology
Solar
Status
active
Location
Granville, NC
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarDukeLBNL

55 MW generation in Granville, NC · In queue since September 2024

55 MW

Capacity

1

Components

Solar

1y 6m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 6m

Impact Study25%
Queue EntrySep 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NC

County

Granville

Region

Southeast

Developer

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

Henderson - Roxboro 115 kV

Data Source

LBNL

No news available for this project.