— Project Summary

Queue ID
Duke-962896
Capacity
74.9 MW
Technology
Solar
Status
active
Location
Marlboro, SC
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarDukeLBNL

74.9 MW generation in Marlboro, SC · In queue since September 2024

74.9 MW

Capacity

1

Components

Solar

1y 6m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 6m

Impact Study25%
Queue EntrySep 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

SC

County

Marlboro

Region

Southeast

Developer

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

Bennettsville Sw Sta - Laurinburg 230 kV

Data Source

LBNL

No news available for this project.