— Project Summary

Queue ID
Duke-962757
Capacity
70 MW
Technology
Solar
Status
active
Location
Lee, SC
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarDukeLBNL

70 MW generation in Lee, SC · In queue since September 2024

70 MW

Capacity

1

Components

Solar

1y 6m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 6m

Impact Study25%
Queue EntrySep 26, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

SC

County

Lee

Region

Southeast

Developer

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

DARLINGTON COUNTY PLANT - FLORENCE 230KV LINE

Data Source

LBNL

No news available for this project.