BetaActiveSolarDukeLBNL
130 MW generation in Stokes, NC · In queue since September 2024
130 MW
Capacity
1
Components
Solar
1y 6m
In Queue
Cluster Study
IA Status
Interconnection Timeline
Total Duration
1y 6m
Impact Study25%
Queue EntrySep 24, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NC
County
Stokes
Region
Southeast
Developer
—
Utility
Duke Energy Carolinas
Entity
Duke
Point of Interconnection
PINE HALL 100kV
Data Source
LBNL
No news available for this project.