BetaActiveSolarDukeLBNL
80 MW generation in Chesterfield, SC · In queue since September 2024
80 MW
Capacity
1
Components
Solar
1y 6m
In Queue
Cluster Study
IA Status
Interconnection Timeline
Total Duration
1y 6m
Impact Study25%
Queue EntrySep 25, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
SC
County
Chesterfield
Region
Southeast
Developer
Duke Energy Progress LLC
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
Darlington County Plant - Florence 230 kV
Data Source
LBNL
No news available for this project.