— Project Summary

Queue ID
Duke-962635
Capacity
80 MW
Technology
Solar
Status
active
Location
Chesterfield, SC
Region
Southeast
Developer
Duke Energy Progress LLC
IA Status
Cluster Study

BetaActiveSolarDukeLBNL

80 MW generation in Chesterfield, SC · In queue since September 2024

80 MW

Capacity

1

Components

Solar

1y 6m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 6m

Impact Study25%
Queue EntrySep 25, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

SC

County

Chesterfield

Region

Southeast

Developer

Duke Energy Progress LLC

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

Darlington County Plant - Florence 230 kV

Data Source

LBNL

No news available for this project.