— Project Summary

Queue ID
Duke-961214
Capacity
48 MW
Technology
Solar
Status
active
Location
Chesterfield, SC
Region
Southeast
Developer
Masked
IA Status
Cluster Study

BetaActiveSolarDukeLBNL

48 MW generation in Chesterfield, SC · In queue since September 2024

48 MW

Capacity

1

Components

Solar

1y 6m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 6m

Impact Study25%
Queue EntrySep 27, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

SC

County

Chesterfield

Region

Southeast

Developer

Masked

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

ROBINSON PLANT - ROCKINGHAM 115KV - FLORENCE

Data Source

LBNL