— Project Summary

Queue ID
Duke-957688
Capacity
5 MW
Technology
Gas
Status
active
Location
Buncombe, NC
Region
Southeast
Developer
Duke Energy Progress LLC
IA Status
Cluster Study

BetaActiveGasDukeLBNL

5 MW generation in Buncombe, NC · In queue since June 2024

5 MW

Capacity

1

Components

Gas

1y 9m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 9m

Impact Study25%
Queue EntryJun 20, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NC

County

Buncombe

Region

Southeast

Developer

Duke Energy Progress LLC

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

Asheville Plant Substation 115kV

Data Source

LBNL

No news available for this project.