BetaActiveGasDukeLBNL
8 MW generation in New Hanover, NC · In queue since June 2024
8 MW
Capacity
1
Components
Gas
1y 9m
In Queue
Cluster Study
IA Status
Interconnection Timeline
Total Duration
1y 9m
Impact Study25%
Queue EntryJun 24, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NC
County
New Hanover
Region
Southeast
Developer
Duke Energy Progress LLC
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
Sutton Plant Substation 115kV
Data Source
LBNL
No news available for this project.