— Project Summary

Queue ID
Duke-957336
Capacity
74.9 MW
Technology
Solar
Status
active
Location
Onslow, NC
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveSolarDukeLBNL

74.9 MW generation in Onslow, NC · In queue since June 2024

74.9 MW

Capacity

1

Components

Solar

1y 9m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 9m

Impact Study25%
Queue EntryJun 28, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NC

County

Onslow

Region

Southeast

Developer

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

JACKSONVILLE - NEW BERN 230KV

Data Source

LBNL

No news available for this project.