— Project Summary

Queue ID
Duke-956971
Capacity
28 MW
Technology
Gas
Status
active
Location
Rowan, NC
Region
Southeast
Developer
IA Status
Cluster Study

BetaActiveGasDukeLBNL

28 MW generation in Rowan, NC · In queue since June 2024

28 MW

Capacity

1

Components

Gas

1y 9m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 9m

Impact Study25%
Queue EntryJun 11, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NC

County

Rowan

Region

Southeast

Developer

Utility

Duke Energy Carolinas

Entity

Duke

Point of Interconnection

BUCK CTCC STA YARD 230 kV

Data Source

LBNL

No news available for this project.