87 MW generation in Moore, NC · In queue since June 2024
87 MW
Capacity
1
Components
Solar
1y 9m
In Queue
Cluster Study
IA Status
Interconnection Timeline
Total Duration
1y 9m
Impact Study25%
Queue EntryJun 27, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NC
County
Moore
Region
Southeast
Developer
Masked
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
CAPE FEAR PLANT - BISCOE 230KV SUB 115KV
Data Source
LBNL