— Project Summary

Queue ID
Duke-956321
Capacity
60 MW
Technology
Battery
Status
active
Location
Chesterfield, SC
Region
Southeast
Developer
Masked
IA Status
Cluster Study

BetaActiveBatteryDukeLBNL

60 MW storage in Chesterfield, SC · In queue since June 2024

60 MW

Capacity

1

Components

Battery

1y 9m

In Queue

Cluster Study

IA Status

Interconnection Timeline

Total Duration

1y 9m

Impact Study25%
Queue EntryJun 26, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

SC

County

Chesterfield

Region

Southeast

Developer

Masked

Utility

Duke Energy Progress

Entity

Duke

Point of Interconnection

ROBINSON PLANT - ROCKINGHAM 230KV - FLORENCE

Data Source

LBNL