BetaActiveBatteryDukeLBNL
50 MW storage in Nash, NC · In queue since June 2024
50 MW
Capacity
1
Components
Battery
1y 9m
In Queue
Cluster Study
IA Status
Interconnection Timeline
Total Duration
1y 9m
Impact Study25%
Queue EntryJun 19, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NC
County
Nash
Region
Southeast
Developer
Duke Energy Progress LLC
Utility
Duke Energy Progress
Entity
Duke
Point of Interconnection
SPRING HOPE 115KV SWITCHING STATION
Data Source
LBNL
No news available for this project.