80 MW generation in Nash, NC · In queue since June 2017 · Proposed COD July 2025
80 MW
Capacity
1
Components
Solar
8y 9m
In Queue
Construction
IA Status
COD target: 2025
Total Duration
8y 1m
Schedule
8 months past proposed COD
Interconnection request submitted to ISO/RTO
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2025-07-31
State
NC
County
Nash
Region
Southeast
Developer
Duke Energy Progress, LLC
Utility
Duke Energy Progress
Entity
Duke
Data Source
LBNL
Duke Energy Progress, LLC, Duke Energy Carolinas, LLC; Notice of Application of Transfer of License and Soliciting Comments, Motions To Intervene, and Protests
Duke Energy Progress, LLC; Duke Energy Carolinas, LLC; Notice of Application of Transfer of License and Soliciting Comments, Motions To Intervene, and Protests
Duke Energy Progress, LLC; Duke Energy Carolinas, LLC; Notice of Application of Transfer of License and Soliciting Comments, Motions To Intervene, and Protests
Duke Energy Progress, LLC; Duke Energy Carolinas, LLC; Notice of Application of Transfer of License and Soliciting Comments, Motions To Intervene, and Protests
Last updated 2026-03-25